DONNELLSON – A $3.5 million expansion of the Central Lee elementary school has been put on hold due to project bids above expected estimates.
At Tuesday’s regular board meeting, the board voted unanimously to reject all project and bond bids for the project with an aim to rebid the project in the fall of 2026.
Superintendent Dr. Andy Crozier recommended the rejection saying the move just wasn’t in the district’s best interests currently.
“I make the recommendation that we reject the construction bids and the bond bids today,” said Superintendent Dr. Andy Crozier.
“The bond bids are in there, too, because if we do this process again in the fall, the interest rates might be better. I don’t know about construction costs at that point. And obviously, we know the world doesn’t get cheaper each month or each year you prolong something. But at this point, I don’t feel like this is the right move for the district.”
Kendall Deter, a pre-Construction Manager with Estes Construction, said the project came in over budget because the original estimates were overly optimistic considering the small footprint of the project. He also said several of the bid packages only garnered one bid.
But he agreed that bidding could be more favorable in the fall as prices continue to stabilize in the market as well as redefining the scope of the project a little bit around concrete.
“On the next go-round let’s get some changes implemented and, unfortunately, we had a couple packages with just a single bid and we need to do a little more reconnaissance on why that was,” Deter said.
“While the costs may go up we don’t have the whole crystal ball. We know labor costs are not going to go down. Materials are the fluctuating factor, and we haven’t seen a lot of cost escalation in the last year or two so, hopefully, that trend continues.”
Board member Brock Westfall said he wasn’t excited about pushing the project down the road but understood the reasons why. The project at $3.5 million was for four classrooms, with the fourth classroom being bid as an alternative package.
“I’m for the four classrooms. I just want that out there,” Westfall said.
“I don’t like pushing this down the road. I know it’s more and I don’t like spending money. I struggle with pushing this. But I know from sitting in on earlier meetings, I had my mind set at $4 million. I really did. But I get it.”
Mark Hulsebus made the recommendation that the district reject the construction bids and the four bids for borrowing against the district’s SAVE funds.
Crozier said the district put in 12 months of work and to deny it at the last minute is disappointing.