FORT MADISON – The phases to consolidate the city’s public works departments into at least one new facility drew heavy conversation at Tuesday night’s regular City Council meeting.
Fort Madison Public Works Director Mark Bousselot presented the council with an update on construction plans for a 15,000 square foot facility that will house much of the equipment being moved from the outdated current facility off Avenue L.
The new Fort Madison Fire Department is planned for construction in the same area and requires that some of the current public works buildings be demolished. City Councilman Matt Emmett said several of those buildings are being held up “by the styrofoam insulation” and new space for the city’s equipment is needed.
Bousselot proposed two phases for the consolidation. Initially they looked at one new location for the entire department near the airport, but that option wasn’t feasible with airport regulations or cost.
City staff then looked at six existing warehouse type properties in town and said the cost of renovations and acquisition exceeded budgeted funding.
“So we're looking at a design of phase one which is, more or less, a storage facility. It's 15,000 square feet that'll store our vehicles and supplies and it's 100% designed and ready to go out to bid,” Bousselot said.
He said the building, which is planned to be located in the 2100 block of Avenue M west of the Fort Madison Community Schools' Central Office, is designed to allow vehicles to drive thru instead of having to back out.
He said phase 2 would be extending the building to the east with modifications into the water distribution building. He said that would fully consolidate the public works department.
The Phase 1 building is estimated at $1.9 million.
City Manager Laura Liegois said that amount is doable with current funding in the department, but the city could consider a small bond if other factors come into play. She said the city budgeted $2 million for the building.
“We have we found out in designing this, other things we had to do to have that size of a building. We had to put it in sprinkler protection, we had to put in drainage, and we had to address stormwater,” she said.
“If we were today to fund this, yes we have resources in the public works department budget that could make this happen.”
Liegois said, however, that the city is planning for additional capital improvements and a “small bond” may be appropriate toward the cost of the building to allow some other smaller projects to be completed.
Bousselot said the timeline is to get the project out to bid and plan to open those on Sept. 2. A public hearing and award of contract is set for the Sept. 16 council meeting and Sept. 29 construction would start on phase 1.
He said one building that needs to come down for the future Fire Department would be left up over the winter and be taken down in March with a building completion of May 4. The Fire Department would start in March or April of 2026.
Bousselot said the phase 1 building wouldn’t be enough for full consolidation.