FORT MADISON – Fort Madison Mayor Matt Mohrfeld once again has raised his eyebrows at additional costs for infrastructure projects in the city.
Tuesday evening, Mohrfeld questioned City Public Works Director Mark Bousselot on why the city is incurring slightly more than $100,000 in change orders as part of the Avenue L overlay project from 20th to 30th Streets.
The increase results from three change orders, two which increase the cost of the project, and one that provides a little relief.
The majority of the cost comes from what appears to be an oversight on the work done several years ago when the intersection of Avenue L and 27th Street was redone. Councilman Rusty Andrews summarized that everyone assumed the entire intersection was reconstructed when it was angled between Walgreens and Hy-Vee, however, that doesn’t seem to be the case.
“I think some people had in their mind that 27th was done knowing the level of survey he did because this is a mill and overlay. He surveyed every inch of that thing, you know. It is kinda disappointing he didn't say 27th St. isn't completely replaced,” Andrews said.
Bousselot said evidently that project included patching some spots, but not replacing the concrete and he noticed this when he was setting up detours for the project currently underway.
“When this happened I wasn't here, but I think the engineer was under the assumption that the pavement on Avenue L had been replaced because we realigned everything. As they were out looking and surveying, they're seeing that the sections of roadway at the intersection of Avenue L has further deteriorated,” Bousselot said.
Warner Engineering Associates out of Mt. Pleasant did the design work on the project.
“I went out there and took a look, and what happened is when we did the realignment of 27th, we didn't redo the intersection.”
He said new concrete was placed from the curb line south on 27th and new concrete was placed from the curb line north on 27th and there is a patch in the two westbound lanes around the manhole that is new, but everything else is the old, existing pavement.
“So these quantities were not in the original contract. This is more or less an adjustment of all the quantities that would be associated with milling to the intersection, pouring the concrete, fixing the curb, and then tying back in on 27th going northbound and southbound for a total of $131,065.38,” he said.
The total project now will cost the city $2,523,907, an increase of $108,000 over the original contract of $2,415,777 with Jones Contracting Corp. of West Point.
“So when we designed this, we just blindly assumed that this was good. Nobody walks this project. We hire a professional engineer, they run a survey, and nobody renders an opinion on this intersection, nobody says anything,” Mohrfeld said.
Comments
No comments on this item Please log in to comment by clicking here