FORT MADISON – Rumors were circulating that Fort Madison City Hall was going to be packed for Tuesday night’s Planning and Zoning Commission meeting. The rumors were true - so much so that more than 100 hundred residents spilled out into the parking lot due to occupancy restrictions.
Residents were there to talk about the proposed data center that is being planned on the east side of Fort Madison where Hwy. 61 comes down the hill into the city.
The P&Z meeting agenda had two items for discussion. One was data center code review and the other was state code that allows the city to create a two-mile territorial zoning jurisdiction by ordinance.
The data center code review took all the 90 minutes allotted for the meeting with City Building Director Doug Krogmeier outlining a proposed ordinance for what he called High Impact Infrastructure.
“As we began to research it and we were looking at data centers, it became apparent to us that it wasn’t just data centers. There are other things that fit this criteria that are going to come down the pipe at some point,” Krogmeier said.
He said data centers fall into the Industrial 2 zoning and there aren’t a lot of restrictions in that code.
“Codewise, Fort Madison needs to do something with this. We need to adopt something. We need to adjust. Whether that’s restrictions or how deep of restrictions, and that’s what we’re going to talk about. What does that look like?”
Krogmeier said residents should provide as much research as they can to help the city.
“There’s a lot of different topics that come into play. Water use, electric use, those are the big ones that everyone’s talking about. We’ve had conversations with Alliant, and there’s not a concrete answer,” he said.
“We can’t say to them 'you can’t pass that to anybody else'. We can’t do that, but we can write development agreements that say what the developer is 100% on the ticket for, and Alliant hopefully sends us back something saying they agree to that.”
He said noise and heat dissipation are also issues.
“Trust me - we are no experts on this and we are researching it, just like you are. We can go through the fine points of that, but right now, we’re not defining those criteria today, it’s an overview of what a code would look like,” he said.
Any code the city would consider would have to go through P&Z review, legal review, and council consideration before being read into the record up to three times. And no action was taken by the committee Tuesday night.
City Manager Laura Liegois told the crowd the city does not have jurisdiction over any projects currently underway on the hill with the exception of two small parcels of land, of which she said would be buffers for city residents and the city didn’t have to allow construction on those pieces.
But residents spoke clearly in opposition not only to the project, but the lack of transparency around it. Because the property is mostly in county jurisdiction and not in city limits, the city didn’t have standing with the developer, Dustin Wolgemuth. The county has no zoning restrictions around data centers so there was no regulation by that body either.
The panel, chaired by local realtor Barb Asay, referred most of the residents’ questions to Lee County, but said she was happy to see so many people out to learn about how the city was moving forward with future projects.