DONNELLSON – The Central Lee School board is weighing options on how to fund an estimated $4 million facility upgrade at the PreK-8 building.
The board held a special workshop on Tuesday to listen to about 90 minutes of financing options from Matthew Gillaspie, Managing Director at Piper Sandler out of Des Moines.
No decisions were made at the workshop, but Gillaspie rolled out four options for the project: On-hand cash and grants; SAVE funds (Sales Tax Revenue Bonds); General Obligation Physical Plant and Equipment Levy Funds; and General Obligation Bonds.
The district wouldn’t have cash on hand to fund the project, which would add four classrooms, additional restrooms, and a corridor connecting district entryways and hallways.
The project was slated to begin last fall, but then Superintendent Dr. Andy Crozier recommended against moving forward after bids came in over budgeted costs. The district was going to borrow against SAVE funds for the work, but that was put off when the project was shuttered.
The district is now looking at the project again and Gillaspie estimated the work, based on figures received from the district, at $4.5 million for financing projections.
Gillaspie said the district could borrow up to $9.1 million against the one-cent sales tax SAVE revenue. With changes to the state property tax code, the district Revenue Purpose Statement, which was approved by a majority of district voters in 2025, is now good through 2071. However, in those same property tax law changes, the state will escalate diversions from the SAVE funds to property tax relief with a cap at 25% in 2030. Gillaspie said the state has already been diverting some of the funds to property tax relief, but in low percentages and sales tax growth has resulted in increased funding despite the diversions.
Central Lee hasn’t collected a board approved PPEL or a voter-approved PPEL since 2020 when they completed the high school renovations. The board cannot borrow against a board-approved PPEL levy, which is typically 0.33/$1,000. A voted PPEL, which would require a ballot measure in March, September, or November of a non-federal election year, would require a simple majority. That levy is typically set at .67/$1,000 assessed valuation or $1.34/$1,000. If that option were taken and approved, the board would be able to borrow against up to 10 years of that revenue stream. At the .67 levy, that would generate up to $2.4 million, and the $1.34 rate it would double that to $4.8 million.
A general obligation bond would require a 60% supermajority. The district could do one ballot measure for up to $2.70/$1,000 assessed valuation, but anything over that would require an additional question on the ballot to exceed the $2.70 rate. G.O. bonds can only be placed on November ballots. A 20-year bond would generate up to $7.2 million while a 20-year G.O. bond at $4.05 would generate up to $16.2 million.
There would be options to pay off the bonds early, but that would be determined by a call date that was built into the bond resolution language by Piper Sandler. Gillaspie said the longer out the call date is, the lower the interest rate would be.
The state caps district debt limits at 5% of the assessed valuation of the district and, for Central Lee, that figure is $39,715,608. The district currently has about $10 million left on the bonds for the high school renovations, leaving them with a debt ceiling of just under $30 million currently.