IAAP

EPA's permit cites "imminent" threat from lead azide

EPA permit says leaving the azide in place presents unacceptable risk to community, environment

Posted

MIDDLETOWN -  A permit issued Monday has the Environmental Protection Agency signing off on the detonation of the barrels of lead azide that are currently stored  underground at the Iowa Army Ammunition Plant in Middletown, Iowa.
The U.S. Army plans to detonate 68 barrels of lead azide with two detonations at about noon Friday afternoon. The event has garnered the attention of most news outlets in the state and several protestors.
A petition was started to stop the blasts and one group is planning described “peaceful protests” prior to the detonations.
The EPA issued an emergency permit in late September that allowed the facility to hold the volatile recrystallized azide in tanks outside of the normal permitting due to the degradation of the chemical. However, according to the permit issued this week, U.S. Army officials determined the azide to be too dangerous in its current state and storage and authorized the detonation.
The EPA's  emergency permit became effective on November 13, 2026, for the storage and treatment of the hazardous waste by in-place, intentional detonation at a location not covered by the existing effective Resource Conservation and Recovery Act (RCRA) permit. The permit wasn’t publicly available until Nov. 16 on the EPA website.
IAAP’s existing RCRA permit authorizes treatment, storage, and disposal of hazardous waste in hazardous waste management units at the facility. However, the storage and treatment of this lead azide hazardous waste is in a location not covered for treatment, storage, or disposal under the effective RCRA permit, according to the newly issued permit. The recrystallization of the stored lead azide has increased the material’s sensitivity to friction and shock, and disturbing the containers of lead azide could create an unacceptable risk of unintentional detonation. The Army’s evaluation of a range of potential alternatives for the treatment of lead azide culminated in the Secretary of the Army, Adam R. Telle, selecting in-place, controlled, intentional detonation.
The EPA wrote in the permit that it was required to protect human health and the environment and the detonations are to safely manage the explosive hazard and mitigate an “imminent” threat to the surrounding community and environment.
The permit requires collection of samples and monitoring before, during and after the detonations, public notifications both before and after the detonation, implementation of clean-up and reporting requirements.
The permit is effective through Feb. 11, 2027.
Pen City Current sent communications to press officers with Iowa Governor Kim Reynolds’ office, Gov-Elect Rob Sand, and to State Sen. Jeff Reichman and State Rep. Blaine Watkins.
Reichman responded writing he didn’t like the situation. 
“I definitely don’t like the fact that it’s going to be such a large ‘controlled explosion’ that it could cause localized damage outside of the ammunition plant,” he wrote.
“Several months ago, we heard about this problem. From that time, a lot of experts with explosives, the plant, and the EPA have come up with what they feel is the best course of action and mitigation plan.”

Photo Caption
Reichman said there isn’t an option to do nothing because the situation is just getting worse and would eventually result in an uncontrolled explosion.  He said he would have preferred more, smaller detonations in order to reduce the explosive arc.
A spokesperson for Iowa Gov. Kim Reynolds said her office was made aware of the detonations  on Monday after a public advisory was issued by the Army. Members of the governor’s staff and state agencies contacted IAAP and the U.S. Army and have since been meeting about the situation.   
Projected impacts of the detonations could result in lead being dispersed through the air to the northeast as far as Muscatine. Many schools, including Burlington and West Burlington are canceling classes for Friday to avoid the impact of the detonations on those days.
Due to the potential for localized window damage, the U.S. Army recommends that residents in the Middletown City Park neighborhood temporarily vacate the area during the detonations out of an abundance of caution.  Residents are asked to vacate starting at 8 a.m. when the explosives team begins setting up the detonations. If residents need a place to stay, they are invited to come to the US Army Reserve Center/Iowa Army National Guard Center at 17879 Highway 79, Middletown, IA.  All family members are welcome, including pets.  Please ensure pets are appropriately secure in carrying containers or on leashes. Refreshments will be available at this relatively new building, complete with a gym and classrooms. It is the same location as the open house the Army hosted on the detonation.  
The U.S. Army has taken extraordinary measures to mitigate the plume by following strict permit requirements set by the EPA, such as earthworks, soil wetting, and air sampling.
Pre-controlled detonation sampling has taken place; air monitors have been established for perimeter air monitoring during the event; and environmental sampling of the blast radius will take place.
The Army has also welcomed media to the reserve center to view the detonation.
The U.S. Army Sustainment Command released additional details on the detonations late Wednesday. Those Friday detonations are planned to be consecutive rapid detonations.
The lead azide barrels will be detonated inside earth-covered magazines made of concrete, and surrounded with Hesco barriers full of sand which are approximately two stories high. Before and during the detonation, the soil above the earth-covered magazines will be thoroughly saturated with water, and water misters will be spraying. These measures should reduce the amount of lead that migrates from the detonation through the air off the installation.
Extensive modeling efforts predict the potential level of lead particles in the air may be elevated but well below the level at which EPA would require protective actions be taken. The detonation will result in an air plume with some lead-containing particles which will disperse in the air and deposit on the ground.
The EPA plays a pivotal role in lead poisoning prevention through a variety of regulatory measures and enforcement actions aimed at reducing exposure to various environmental media contaminated with lead, including soil. This detonation has been planned and approved in coordination with the EPA under the Resource Conservation and Recovery Act. The Army has taken extraordinary measures to mitigate the plume through earthworks, soil wetting, and water spraying. Pre-controlled detonation sampling has taken place; air monitors have been established for perimeter air monitoring following the event; and environmental sampling of the blast radius will take place. You can learn more about lead in soil here: https://www.epa.gov/lead/lead-soil.

Public inquiries should be sent to usarmy.ria.asc.list.pa@army.mil

news, Lee County, IAAP, lead azide, Pen City Current, detonations, explosions, Iowa, Environmental Protection Agency, permits,

Comments

No comments on this item Please log in to comment by clicking here